Track Record
Steel Structures
Follows specific standards and mechanisms using steel as a constructing material. We construct innovative steel structures beam, column, strut, frame,cross sectioned,triangular rigid structure etc.
Instrumentation Works
Eyota extends it service in instrumentation through a well organised and creative team that designs, installs and manages equipments that monitor and control systems or machineries through engineering.
Mechanical Works
Exotic materials are used in manufacturing and Piping is used with high quality and durability. We have a highly qualified expert team to handle projects from new builds to brownfield modifications.
Project List
Sl.No. | Project Description | Year | Location | Client | Owner | Status |
---|---|---|---|---|---|---|
1 | ||||||
2 | Installation of 5 Units of Dust Collectors | 2019-2020 | India Sri city Tada | Sankyu India Logistics & Engineering Pvt Ltd | Daiki Aluminium Industry India Pvt Ltd | Completed |
3 | Gas Holder Tank Fabrication | 2019 | Malaysia | JEL Maintenance Pte Ltd | Sumitomo Chemical Engineering Singapore | Completed |
4 | Independent House Construction | 2019-2020 | India Chennai | Singapore Client | Singapore Client | On going |
5 | Deputation of Technical Resource | 2018-2020 | Trinidad West indies | Mitshubishy Heavy Industries Engineering Ltd. Japan | Caribbean Gas Chemical Limited | Completed |
6 | Design, Supply & Erection Of Structural | 2018-2019 | India Hyderbad | Royals Marine Food Pvt Ltd | Royals Marine Food Pvt Ltd | Completed |
7 | Master Plan -VBR business Park Architects & Structural & MEP & QC | 2019 | India Vijayawada | Infrakruthi Developers Pvt Ltd | Infrakruthi Developers Pvt Ltd | Completed |
8 | Design, Supply, Installation, Testing and Commissioning and Handing over of Fire Protection Works | 2017-2018 | India New Delhi | L&W Construction Pvt Ltd | Ascendas Service India Pvt Ltd | Completed |
9 | Design, Supply, Installation, Testing and Commissioning and Handing over of PHE | 2017-2018 | India New Delhi | L&W Construction Pvt Ltd | International Infrabuild Pvt Ltd | Completed |
10 | Design, Supply, Installation, Testing and Commissioning and Handing over of PHE | 2017-2018 | India New Delhi | L&W Construction Pvt Ltd | Ascendas Service India Pvt Ltd | Completed |
11 | Statutory Liasoning | 2017-2018 | India Chennai | L&T Geo Structure | IndianOil LNG Pvt Ltd | Completed |
12 | Statutory Liasoning | 2017-2019 | India Chennai | KSS Petron Pvt Ltd | IndianOil LNG Pvt Ltd | Completed |
13 | Statutory Liasoning | 2017-2020 | India Chennai | Mitshubishy Heavy Industries | IndianOil LNG Pvt Ltd | On going |
14 | Construction of DG & Transformer Pedestal and Cable Trench- Main HT Panel Room | 2017-2017 | India Hyderbad | VITP Pvt Ltd (Ascendas) | Ascendas Service India Pvt Ltd | completed |
15 | Deputation of Skilled Resource | 2017 | Malaysia | ASIAGROUP SDN BHD | Petronas Rapid | Completed |
16 | Mechanical &Electrical Construction IP76 Drilling/Tapping | 2017-2017 | India Madhya Pradesh | Procter & Gamble Home Products Limited | Procter & Gamble Home Products Limited | Completed |
17 | Manufacture of Booster After Cooler -Shell and Tube Heat Exchanger | 2016-2017 | India Hyderbad | Extol Infracon India Pvt Ltd | Extol | Completed |
18 | Deputation of Skilled Resource | 2016-2016 | India Madhya Pradesh | Sankyu India Logistics & Engineering Pvt Ltd | Procter & Gamble Home Products Limited | Completed |
19 | Deputation of Technical Resource | 2015-2019 | India Chennai | Mitshubishy Heavy Industries | IndianOil LNG Pvt Ltd | Completed |
20 | Procurement & Construction of Two storey Machnical Work shop building along with temp facilities at SCA Trex (SSBR) Project. jurong Island | 2017-2018 | Singapore | Sumitomo Chemical Engineering Singapore | Singapore Chemical Asia | Completed |
21 | Procurement & Construction of Max expansion project at Kuraray Asia Pacific Pte Ltd, Jurong Island | 2017-2018 | Singapore | Sumitomo Chemical Engineering Singapore | Kuraray | Completed |
22 | Procurement & Construction of compressor foundation replacement filed works project at Chevron Philips Singapore | 2017-2018 | Singapore | Sumitomo Chemical Engineering Singapore | Chevron Philips Singapore | Completed |
23 | Procurement & Construction of Iso tanker station, process area and truck scale with temp facilities at SMAG, Jurong Island | 2017-2018 | Singapore | Sumitomo Chemical Engineering Singapore | Singapore Acrylic Pte Ltd | Completed |
24 | Procurement & Construction of sodium bi carbonate processing & packing unit. Phase-1 | 2016-02-17 00:00:00 | Singapore | JEL Maintenance Pte Ltd | Novabay Pte Ltd | Completed |
25 | Procurement & Construction of sodium bi carbonate processing & packing unit. Phase-2 | 2016-02-17 00:00:00 | Singapore | JEL Maintenance Pte Ltd | Novabay Pte Ltd | Completed |
26 | Procurement & Construction of container loading bay shelter for Vanning project at Kuraray Asia Pacific | 2015-2016 | Singapore | Sumitomo Chemical Engineering Singapore | Kuraray | Completed |
27 | Procurement & Construction of Gas Diversion Builders work for proposed Development of an aviation related mixed used of complex at T1 Changin Airport | 2014-2015 | Singapore | Mott Maconald | Jewel Changi Airport Group | Completed |
28 | Design and Construction of Drum Storage shed and Cold Room works for Pfizer, Tuss | 2014-2015 | Singapore | Pfizer Asia Pacific Pte Ltd | Pfizer | Completed |
29 | Design, Supply and Construction of Loop reactor structure and raw material facilities for GPS II Porject at TPC plant, jurong | 2014-2015 | Singapore | Sumitomo Chemical Engineering Singapore | The Polylefin Company | Completed |
30 | Construction of Temporary Facility works for TPC Project, Jurong Island | 2014-2015 | Singapore | Sumitomo Chemical Engineering Singapore | The polylefin Company | Completed |
31 | Construction Concrete slab works for Dupont, Tuss. | 2014-2015 | Singapore | JEL Maintenance Pte Ltd | Dupont | Completed |
32 | Procurement & Construction of Tank Yard monomer cooling system project for Unimatec at Jurong island. | 2014-2015 | Singapore | Sumitomo Chemical Engineering Singapore | Unimatec | Completed |
33 | Construction of bund wall foundation and stumps for Vopak project, Jurong Island. | 2014-2015 | Singapore | JEL Maintenance Pte Ltd | Vopak Terminals | Completed |
34 | Construction of cable Duct bank and cable rack for shell pandan silver project. | 2014-2015 | Singapore | Sumitomo Chemical Engineering Singapore | Shell Eastern Petroleum | Completed |
35 | Construction of bound wall extension works for shell pandan silver project. | 2014-2015 | Singapore | Sumitomo Chemical Engineering Singapore | Shell Eastern Petroleum | Completed |
36 | Waste Water Removal & Underground Tank clearance work at SUT Jurong Island | 2014-2015 | Singapore | JEL Maintenance Pte Ltd | Sembcorp | Completed |
37 | Procurement & Construction Plant Civil Footing works & Fencing Works for solway Fire Water project | 2014-2015 | Singapore | JEL Maintenance Pte Ltd | Solway | Completed |
38 | Procurement & Construction Plant civil & structural works including piling works KAP 3rd Dryer Project | 2014-2015 | Singapore | JEL Maintenance Pte Ltd | Kuraray | Completed |
39 | Procurement & installation for fencing and Civil foundations works | 2014-2015 | Singapore | Sumitomo Chemical Engineering Singapore | Kuraray | Completed |
40 | Procurement & Construction of concrete blocks with lifting hooks at jurong westward extension project | 2014-2015 | Singapore | DIAP - SHAP JV | JTC | Completed |
41 | Procurement & installation for fencing and Civil footing works | 2014-2015 | Singapore | Hertel Singapore Pte Ltd | Stolthaven Terminal | Completed |
42 | Procurement & Laying of Hardcore and Gravel works with concrete slab at Jurong westward extension Project | 2014-2015 | Singapore | DIAP-SHAP JV | JTC | Completed |
43 | Procurement & Construction of Settlement Market at Jurong Westward extension Project | 2014-2015 | Singapore | DIAP-SHAP JV | JTC | Completed |
44 | Trail Trench Excavation works at Jurong Island | 2014-2015 | Singapore | Sumitomo Chemical Engineering Singapore | Kuraray | Completed |
45 | Procurement & Construction plant Civil works | 2014-2015 | Singapore | OGSP Enigneering Pte Ltd | O BASF Chemical Company | Completed |
46 | Procurement & Construction Civil foundation & Structural Platforms including Piling works | 2014-2015 | Singapore | JEL Maintenance Pte Ltd | The Polyolefin Company | Completed |
47 | Procurement & Construction of weighbridge at Jurong westward extension Project | 2014-2015 | Singapore | DIAP-SHAP JV | JTC | Completed |
48 | Procurement & Construction of cable trench, slab paving and installation of UPVC pipes – Holland Shaft | 2014-2015 | Singapore | SK E&C | SP Power Services | Completed |
49 | Procurement & Construction of Gantry Crane rail Foundation & Drain works-Duneam shaft | 2013-2014 | Singapore | SK E&C | SP Power Services | Completed |
50 | Reber installation, drilling and pile hacking works. | 2013-2014 | Singapore | Hyundai Engineering & Construction | HDB | Completed |
51 | Procurement & installation of formworks for concrete colums and beams | 2013-2014 | Singapore | Daewoo E&C | One Balmoral | Completed |
52 | Procurement & Construction of pipe sleeper footing works | 2013-2014 | Singapore | JEL Maintenance Pte Ltd | Sembcorp | Completed |
53 | Fabrication and supply of pipe supports | 2013-2014 | Singapore | Sumitomo Chemical Engineering Singapore | PCS | Completed |
54 | Procurement , Fabrication and erection of fencing and construction of its support footings | 2013-2014 | Singapore | Toa Corporation | HDB | Completed |
55 | Rebar installation, drilling and casting works for MRT station project. | 2013-2014 | Singapore | Hyundai Engineering & Construction- Samdai Yang | LTA | Completed |
56 | Supply & Installation of Polyurethane & Pressure Grouting | 2013-2014 | Singapore | JDC Corp | Lend Lease | Completed |
57 | Procurement of installation of Tank insulation & painting works. | 2012-2013 | Vietnam | Petroleum Maintenance Service Joint Stock Company | Binh Son Refinery | Completed |
58 | Maintenance and repair works for the pipelines | 2012-2013 | Vietnam | Petroleum Maintenance Service Joint Stock Company | Binh Son Refinery | Completed |
59 | Material procurement ad construction of equipment civil foundation (Strengthening) and drains. | 2012-2013 | Singapore | JEL Maintenance Pte Ltd | Sembcorp | Completed |
60 | Supply are installation of the gantry crane runway of 200m | 2012-2013 | Singapore | Keppel Signmarine | Kepple | Completed |
61 | To do the survey for tank settlement before and after the tank lifting for foundation recasting. | 2012-2013 | Singapore | Hertel Singapore Pte Ltd | Vopak Terminals | Completed |
62 | Procurement and install of Ductile iron pipeline for service water lines. | 2012-2013 | Singapore | Keppel Signmarine | Keppel | Completed |
63 | Material procurement and construction of civil Strengthening (A&A)Works | 2012-2013 | Singapore | Jel Maintenance Pte Ltd BASF | O-BASF- Chemical Company | Completed |